Things are moving fast at the moment, so I don't have time to write much, but here's a video taken on the 10th of August, with a walkthrough of the first and second floors. Changes since the last vid include a screed pour in the kitchen to level things out a bit, much progress with plasterboard work, completion of clay plastering on ceilings, and beginning oiling the oak ceiling beams, which look lovely.